How to plan a home renovation

Most renovation problems start before anyone picks up a tool: a budget with no slack, a missed permission, or trades booked in the wrong order. Here is the order that avoids them.

Last checked 20 October 2026 · For homes in England; rules differ in Wales, Scotland and Northern Ireland.

1. Decide what you want, and what it's for

Write down the problem you're solving (a dark kitchen, too few bedrooms, a cold house) before the solution. It keeps the brief short and stops "while we're at it" additions, which are the most common reason budgets grow.

2. Set a budget, then add a contingency

Get a realistic range for the work first. Our free estimator gives a low and a high figure for 30 kinds of job, with materials and labour shown separately. Then keep money aside for the unexpected: once walls are opened and floors lifted, older houses often hide rotten timbers, old wiring or poor foundations. Our high figures already include 10% for surprises on larger jobs; many homeowners keep 10–20% on top of the price they accept.

Remember the costs that aren't building work: architect or designer drawings, a structural engineer, planning and Building Control fees, Party Wall surveyors, and somewhere to live or cook if the house is out of action.

3. Check permissions early

  • Planning permission: many extensions and loft conversions are allowed under permitted development, but not all. See do I need planning permission?
  • Building Regulations: most structural work, new bathrooms, rewiring, boilers and replacement windows need approval or a certificate. See Building Regulations explained.
  • Party walls: work on a shared wall or digging near a neighbour's foundations needs notice. See the Party Wall Act.
  • Leasehold or listed? Flats usually need the freeholder's consent, and listed buildings need listed building consent for most changes.

4. Get designs and a written specification

For anything structural, drawings and a structural engineer's calculations come first. For smaller jobs, a written list of what you want (sizes, finishes, who supplies what) is enough. The more detail you give, the more comparable the quotes will be.

5. Get at least three comparable quotes

Send every builder the same specification and ask for itemised prices. Compare like for like, not just the totals. Our guide on getting and comparing builder quotes covers what to ask and the warning signs.

6. Agree a contract and payment plan

Put the price, what's included and excluded, the start date and rough programme, and how changes will be priced in writing. Pay in stages as work is completed, never most of the money up front.

7. Sequence the work

Builders follow a familiar order, and following it means nothing is done twice:

  1. Strip-out and any demolition
  2. Structural work: foundations, walls, steel beams, roof
  3. First fix: pipes, cables and boxes inside open walls and floors
  4. Plastering, then a few days to dry
  5. Second fix: sockets, switches, radiators, sanitaryware, kitchen fitting
  6. Flooring and tiling
  7. Decorating, then snagging

8. Keep the paperwork

At the end, collect the Building Control completion certificate, electrical and gas safety certificates, window certificates and any guarantees. You'll need them when you sell.